Infrastructure Improvement Project – Week of September 21
Published on Sep 20, 2026 09:41
Construction continues next week as crews make progress on several areas of the City’s infrastructure program.
CONCRETE WORK
Monday, September 21
Concrete work will continue near Joel Street and Ann Arbor Trail.
Tuesday, September 22
Concrete work is anticipated on Evergreen, Goldsmith and near the intersection of Mill and Liberty. Crews may move between locations throughout the day as work is completed.
Wednesday, September 23
Any remaining concrete work is expected to be completed.
RESTORATION
Restoration work will continue along Park Street in Old Village, including seed, straw and mulch blankets.
UPCOMING RESURFACING
Resurfacing of the remaining areas — including Ann Arbor Trail near Joel, Evergreen, William and Goldsmith — is anticipated in the coming weeks. This work will follow the required concrete curing period and completion of structure adjustments.
The City is also coordinating plans for paving on Goldsmith and potentially William. More details to come on this.
Thank you for your continued patience as this work moves toward completion.
Construction schedules are subject to change due to weather, site conditions and other factors.
|