Infrastructure Improvement Project – Week of September 14
Published on Sep 14, 2026 16:47

Construction continues this week at several locations throughout the City. Below is the anticipated schedule:

Monday, September 14
Road milling is planned on Wing, Harding, Maple, Ann Arbor Trail, William and Goldsmith.

Tuesday, September 15
Milling will continue if additional time is needed. Crews are also expected to begin excavation and placement of aggregate base on Joel Street between Sheridan and Ann Arbor Trail. This work may continue into Wednesday.

Wednesday, September 16
Asphalt paving is anticipated on Wing, Harding, Maple, Ann Arbor Trail, William and Goldsmith.

Thursday, September 17
Paving will continue if necessary. Concrete work is also tentatively scheduled on Joel Street and near Mill and Liberty.

Friday, September 18
Concrete work will continue if additional time is needed.

Please note: Construction schedules are tentative and may change based on weather, site conditions, contractor availability and other unforeseen circumstances. Residents and motorists should watch for construction crews, temporary traffic impacts and changing conditions throughout the week.

Questions? Email [email protected] or call 734-453-7737